Oct. 2014-Oct. 2015: BASF and MarkorChem Manufacturing (XinJiang) Co., Ltd. 50KTA Polytetrahydrofuran Project, MPEI Installation, details below:
1. steel structure: 1700 tons
2. storage tanks: 10 sets, 2201m3
3. equipment installation: 183 sets, of which, static equipment 122 sets, dynamic equipment 61sets
4. pipe: 24537 meters, welding quantity 78000DIN, of which CS:51700DIN, SS:26300DIN
5. Electric: 73 sets of equipment in total, of which, 664 sets of lighting fixtures, 3375 meters of cable trays, about 73770 meters of power cables and 26000 meters of e-tracing belts.
6. instruments: 16 sets of DCS cabinets, 138 sets of instrument end boxes, 1112 sets of various instruments and instrument valves, about 131516 meters of instrument cables.
7. insulation and painting: pipeline painting- 5986 m2 in total, steel structure anticorrosive coating-30085 m2 in total, pipeline insulation- 11000 m2, equipment insulation -about 5535 m2
8. HVAC: 61 sets of HVAC equipment in total, duct fabrication and installation - 2500 m2.
The scope of work includes: installation of steel structure, large tank prefabrication, machinery, piping, electrical & instrument, HVAC, laboratory, paint, insulation installation.
Positive comments from the supervision unit of the joint venture project invested by both Xinjiang MarkorChem Group and BASF: neat PPE wearing, good scaffolding set-up, orderly construction organization, technology and schedule management, 99.13% welding qualification rate.